PERMIT #7112045-CN
2801 ALASKAN WAY, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 19, 2025
In Review
2 cycles
Reviews Done
December 29, 2025
Ready to Issue
December 29, 2025
Issued
December 29, 2025
Completed
January 12, 2026
Expires
June 29, 2027
40
Plan Review Days — Total
34
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2801 ALASKAN WAY, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$35,000
Type
Commercial Construction
Issued
December 29, 2025
Location
Other Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
*full plan review required* 70 & Sunny Coffee Co. Tenant improvements for coffee shop (70 & Sunny Coffee Co.) at street level of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0004650
Review cycles
2
Plan review days
40
Days in corrections
6
Expires
June 29, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0