PERMIT #7112073-CN

11707 SAND POINT WAY NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 20, 2025
In Review
0 cycles
Reviews Done
April 17, 2026
Ready to Issue
April 17, 2026
Issued
April 22, 2026
Completed
Expires
October 22, 2027
179
Plan Review Days — Total
179
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$235,923
Type
Residential Construction
Issued
April 22, 2026
Location
Meadowbrook

Contractor Information

Contractor
HERRON HOMES LLC
General Contractor
License HERROHL827P2

Location & Map

Project Description
Herron Sand Point North Construct new middle one family dwelling, per plan. (Establish use as single family residence with detached dwelling units per land use code. Construct 3 one family dwellings, per plan. Review and process for 3 records under 7097768-CN)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HERROHL827P2
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0360020
Review cycles
0
Plan review days
179
Days in corrections
0
Expires
October 22, 2027
Open official SDCI detail →
View Contractor