PERMIT #7112143-CN

5404 20TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 17, 2025
In Review
3 cycles
Reviews Done
December 8, 2025
Ready to Issue
December 8, 2025
Issued
December 8, 2025
Completed
Expires
June 8, 2027
52
Plan Review Days — Total
40
Plan Review Days — City Control
12
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$202,684
Type
Residential Construction
Issued
December 8, 2025
Location
Other Seattle

Contractor Information

Contractor
SEATTLE BUILDING & MGMT LLC
General Contractor
License SEATTBM821MR

Location & Map

Project Description
2530 Construct detached accessory dwelling unit (DADU) accessory to single family residence per standard plan 6794017-SP. Demolish existing detached garage.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SEATTBM821MR
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1154455
Review cycles
3
Plan review days
52
Days in corrections
12
Expires
June 8, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor