PERMIT #7112149-CN

5100 15TH AVE NW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 6, 2025
In Review
2 cycles
Reviews Done
November 25, 2025
Ready to Issue
November 26, 2025
Issued
November 26, 2025
Completed
March 4, 2026
Expires
May 26, 2027
19
Plan Review Days — Total
18
Plan Review Days — City Control
1
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$108,000
Type
Commercial Construction
Issued
November 26, 2025
Location
Other Seattle

Contractor Information

Contractor
PCL CONSTRUCTION SRVC INC
General Contractor
License PCLCOSI099NW

Location & Map

Project Description
Peregrine 15th Ave BLDG *full plan review required* Construct Tenant improvements to existing commercial building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PCLCOSI099NW
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0017166
Review cycles
2
Plan review days
19
Days in corrections
1
Expires
May 26, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor