PERMIT #7112234-CN

4827 49TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 5, 2026
In Review
3 cycles
Reviews Done
July 24, 2026
Ready to Issue
July 27, 2026
Issued
July 27, 2026
Completed
Expires
200
Plan Review Days — Total
78
Plan Review Days — City Control
122
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$770,530
Type
Residential Construction
Issued
July 27, 2026
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct east one-family dwelling per plan. (Establish use as single-family dwelling unit with detached accessory dwelling unit per land use code. Construct (2) one-family dwellings per plan. Review and processing for two records under 7112234-CN)

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1153281
Review cycles
3
Plan review days
200
Days in corrections
122
Units added
1
Units removed
0
Open Map