PERMIT #7112408-CN

3049 NE 90TH ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 3, 2025
In Review
5 cycles
Reviews Done
March 9, 2026
Ready to Issue
March 10, 2026
Issued
March 10, 2026
Completed
May 29, 2026
Expires
September 10, 2027
126
Plan Review Days — Total
107
Plan Review Days — City Control
19
Days in Applicant Control
5
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Wedgwood Neighborhood

Project Overview

Project Details
Value
$74,335
Type
Residential Construction
Issued
March 10, 2026
Location
Wedgwood

Contractor Information

Contractor
Not published by SDCI
License JDREMRC870JC

Location & Map

Project Description
Basement Construct alterations to finish basement of existing single-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JDREMRC870JC
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1149304
Review cycles
5
Plan review days
126
Days in corrections
19
Expires
September 10, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map