PERMIT #7112517-CN
1300 1ST AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
May 28, 2026
In Review
2 cycles
Reviews Done
July 7, 2026
Ready to Issue
July 7, 2026
Issued
July 7, 2026
Completed
—
Expires
—
40
Plan Review Days — Total
29
Plan Review Days — City Control
11
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$74,331
Type
Commercial Construction
Issued
July 7, 2026
Location
Downtown
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to south lobby of existing commercial building (Seattle Art Museum) per plan
Additional Details
Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0017305
Review cycles
2
Plan review days
40
Days in corrections
11
Units added
0
Units removed
0