PERMIT #7112547-DM

4922 50TH AVE S, SEATTLE, WA

new
Construction Permit Timeline
Applied
April 28, 2026
In Review
1 cycle
Issued
Completed
Expires
50
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood
Project Details
Value
$2,000,000
Type
Residential Construction
Issued
N/A
Location
Other Seattle
Contractor
Not published by SDCI
Project Description
Tran New 4 SFR Establish use as vacant land, per land use code. Demolish one-family dwelling, per plan.
Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1110675
Review cycles
1
Days in corrections
50
Open official SDCI detail →