PERMIT #7112840-CN

6301 20TH AVE NW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 25, 2025
In Review
3 cycles
Reviews Done
March 4, 2026
Ready to Issue
March 6, 2026
Issued
March 6, 2026
Completed
Expires
September 6, 2027
99
Plan Review Days — Total
58
Plan Review Days — City Control
41
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$278,309
Type
Commercial Construction
Issued
March 6, 2026
Location
Ballard

Contractor Information

Contractor
RYAN GENERAL CONTRACTORS INC
General Contractor
License RYANGCI930PC

Location & Map

Project Description
Sideris Church Remodel Construct tenant improvements for church (Sideris Church) at main level of existing institutional building, occupy per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
RYANGCI930PC
Review level
Full C
Primary use
Institutional
Parcel
DV0342899
Review cycles
3
Plan review days
99
Days in corrections
41
Expires
September 6, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor