PERMIT #7112847-CN

1215 4TH AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 25, 2025
In Review
2 cycles
Reviews Done
March 24, 2026
Ready to Issue
July 21, 2026
Issued
July 23, 2026
Completed
Expires
119
Plan Review Days — Total
94
Plan Review Days — City Control
25
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$754,000
Type
Commercial Construction
Issued
July 23, 2026
Location
Downtown

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to ground level lobby of existing office building per plan.

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0094857
Review cycles
2
Plan review days
119
Days in corrections
25
Units added
0
Units removed
0