PERMIT #7113165-CN

3807 DENSMORE AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 10, 2025
In Review
4 cycles
Reviews Done
April 9, 2026
Ready to Issue
April 10, 2026
Issued
April 10, 2026
Completed
Expires
October 10, 2027
120
Plan Review Days — Total
85
Plan Review Days — City Control
35
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$860,189
Type
Residential Construction
Issued
April 10, 2026
Location
Wallingford

Contractor Information

Contractor
SEA HOME BUILDERS LLC
General Contractor
License SEAHOHB806DO

Location & Map

Project Description
3807 DENSMORE AVE N - SFR+DADU Establish use as single family residence with attached accessory dwelling unit per Land Use Code. Construct new two-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SEAHOHB806DO
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1215576
Review cycles
4
Plan review days
120
Days in corrections
35
Expires
October 10, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor