PERMIT #7114008-CN

6301 SAND POINT WAY NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 26, 2025
In Review
2 cycles
Reviews Done
January 9, 2026
Ready to Issue
January 12, 2026
Issued
January 13, 2026
Completed
Expires
July 13, 2027
44
Plan Review Days — Total
21
Plan Review Days — City Control
23
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$10,000
Type
Residential Construction
Issued
January 13, 2026
Location
Laurelhurst

Contractor Information

Contractor
L A ENTERPRISES
General Contractor
License LAENT**044KZ

Location & Map

Project Description
Kitchen Remodel/Wall 2025 Construct interior alterations to ground floor condo unit of existing multifamily building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LAENT**044KZ
Review level
Full +
Primary use
Multifamily
Parcel
DV0034924
Review cycles
2
Plan review days
44
Days in corrections
23
Expires
July 13, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor