PERMIT #7115210-CN
4730 UNIVERSITY WAY NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 4, 2025
In Review
0 cycles
Ready to Issue
November 6, 2025
Issued
February 5, 2026
Completed
—
Expires
August 5, 2027
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4730 UNIVERSITY WAY NE, SEATTLE, WA Property
Dallas Legendre Contractor
University District Neighborhood
Project Overview
Project Details
Value
$500,000
Type
Residential Construction
Issued
February 5, 2026
Location
University District
Contractor Information
Location & Map
Project Description
Lothlorien Phase II Complete and final for 6930048-CN, subject to field inspection, STFI
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
FACILMM771DA
Review level
Field
Primary use
Multifamily
Parcel
DV0066808
Review cycles
0
Days in corrections
0
Expires
August 5, 2027