PERMIT #7115450-CN

2045 A N 78TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 10, 2025
In Review
0 cycles
Reviews Done
April 23, 2026
Ready to Issue
April 23, 2026
Issued
June 24, 2026
Completed
Expires
164
Plan Review Days — Total
164
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Green Lake Neighborhood

Project Overview

Project Details
Value
$388,475
Type
Residential Construction
Issued
June 24, 2026
Location
Green Lake

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct SE one-family dwelling per plan. [Establish use as housing for (4) detached dwelling units per land use code. Construct one-family dwellings per plan. Review and processing for (4) construction records under 7114654-CN].

Additional Details

Permit Intelligence
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0056775
Review cycles
0
Plan review days
164
Days in corrections
0
Units added
1
Units removed
0
Open Map