PERMIT #7115465-CN
13513 30TH AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 23, 2026
In Review
2 cycles
Reviews Done
March 6, 2026
Ready to Issue
March 6, 2026
Issued
March 6, 2026
Completed
—
Expires
September 6, 2027
42
Plan Review Days — Total
26
Plan Review Days — City Control
16
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$464,840
Type
Residential Construction
Issued
March 6, 2026
Location
Pinehurst
Contractor Information
Location & Map
Project Description
13513 A & B 30TH AVE NE | 2 New DADUs Construct two DADU attached housing units, per land use code. Construct new two-family dwelling, per plan. Existing one-family dwelling to remain.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BLUESSC929Q5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0017524
Review cycles
2
Plan review days
42
Days in corrections
16
Expires
September 6, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0