PERMIT #7115629-CN

1959 NE PACIFIC ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 7, 2025
In Review
1 cycle
Reviews Done
November 13, 2025
Ready to Issue
November 17, 2025
Issued
November 17, 2025
Completed
Expires
December 15, 2025
6
Plan Review Days — Total
6
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
BNBUILDERS INC Contractor
Montlake Neighborhood

Project Overview

Project Details
Value
$15,000
Type
Commercial Construction
Issued
November 17, 2025
Location
Montlake

Contractor Information

Contractor
BNBUILDERS INC
General Contractor
License BNBUII*990K3

Location & Map

Project Description
UWMC ML Rapid Temp Trailers (3 of 6 max) Temporary installation of factory-built office trailer, steps and ramp for UW Medical Center emergency department administration for 4 weeks, starting at permit issuance, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BNBUII*990K3
Review level
Full +
Primary use
Institutional
Parcel
DV0010348
Review cycles
1
Plan review days
6
Days in corrections
0
Expires
December 15, 2025
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor