PERMIT #7115880-CN

5606 48TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 29, 2026
In Review
3 cycles
Reviews Done
April 29, 2026
Ready to Issue
April 29, 2026
Issued
April 29, 2026
Completed
Expires
October 29, 2027
90
Plan Review Days — Total
27
Plan Review Days — City Control
63
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
BACKYARD ADU LLC Contractor
Rainier Valley Neighborhood

Project Overview

Project Details
Value
$451,212
Type
Residential Construction
Issued
April 29, 2026
Location
Rainier Valley

Contractor Information

Contractor
BACKYARD ADU LLC
Single Family/Duplex
License BACKYAL786JM

Location & Map

Project Description
4803 S Findlay Dev Allow housing for two attached dwelling units, per land use code. Existing detached dwelling to remain. Construct new two-family dwelling, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BACKYAL786JM
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1104923
Review cycles
3
Plan review days
90
Days in corrections
63
Expires
October 29, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor