PERMIT #7116068-DM

9604 MARY AVE NW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 13, 2026
In Review
3 cycles
Reviews Done
June 24, 2026
Ready to Issue
June 24, 2026
Issued
June 24, 2026
Completed
Expires
103
Plan Review Days — Total
45
Plan Review Days — City Control
58
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Crown Hill Neighborhood

Project Overview

Project Details
Value
$1,800,000
Type
Residential Construction
Issued
June 24, 2026
Location
Crown Hill

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Demolish existing one-family dwelling per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1114110
Review cycles
3
Plan review days
103
Days in corrections
58
Units added
0
Units removed
1
Open Map