PERMIT #7116311-BK
535 TERRY AVE N, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 13, 2025
In Review
2 cycles
Reviews Done
December 22, 2025
Ready to Issue
December 23, 2025
Issued
March 10, 2026
Completed
—
Expires
September 10, 2027
39
Plan Review Days — Total
10
Plan Review Days — City Control
29
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
535 TERRY AVE N, SEATTLE, WA Property
TURNER CONSTRUCTION COMPANY Contractor
South Lake Union Neighborhood
Project Overview
Project Details
Value
$12,000,000
Type
Commercial Construction
Issued
March 10, 2026
Location
South Lake Union
Contractor Information
Location & Map
Project Description
535 Terry Ave Blanket TI Construct blanket permit tenant improvements to future tenant on floors: P2, P3, 2, 3, 4, & 5 of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TURNECC237D2
Review level
Full C
Primary use
Commercial
Parcel
DV0059022
Review cycles
2
Plan review days
39
Days in corrections
29
Expires
September 10, 2027