PERMIT #7116455-CN

4840 50TH AVE SW, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
March 20, 2026
In Review
1 cycle
Issued
Completed
Expires
116
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
West Seattle Neighborhood

Project Overview

Project Details
Value
$493,131
Type
Residential Construction
Issued
N/A
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new one family dwelling per plan. Existing buildings to remain.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0029905
Review cycles
1
Days in corrections
116
Open Map