PERMIT #7116461-CN

3013 NE 103RD ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 4, 2025
In Review
4 cycles
Reviews Done
June 23, 2026
Ready to Issue
June 24, 2026
Issued
July 2, 2026
Completed
Expires
201
Plan Review Days — Total
84
Plan Review Days — City Control
117
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Meadowbrook Neighborhood

Project Overview

Project Details
Value
$372,895
Type
Residential Construction
Issued
July 2, 2026
Location
Meadowbrook

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Establish use as single-family dwelling units per Land Use Code. Construct new middle one family dwelling (SFR B) per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1127630
Review cycles
4
Plan review days
201
Days in corrections
117
Units added
1
Units removed
0