PERMIT #7116671-CN
200 SUE BIRD CT N, Seattle, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 5, 2025
In Review
2 cycles
Reviews Done
January 5, 2026
Ready to Issue
January 8, 2026
Issued
January 8, 2026
Completed
—
Expires
July 8, 2027
31
Plan Review Days — Total
25
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
200 SUE BIRD CT N, SEATTLE, WA Property
Belltown Neighborhood
Project Overview
Project Details
Value
$25,000
Type
Commercial Construction
Issued
January 8, 2026
Location
Belltown
Contractor Information
Contractor
Not published by SDCI
License MASTENS863JS
Location & Map
Project Description
SC68 Denny & Broad AT&T RRH SWAP Construct alterations to minor telecommunications facility (AT&T) at the roof level of Pacific Science Center, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS863JS
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0081053
Review cycles
2
Plan review days
31
Days in corrections
6
Expires
July 8, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0