PERMIT #7116803-BK
1000 OLIVE WAY, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 14, 2025
In Review
1 cycle
Reviews Done
November 21, 2025
Ready to Issue
November 21, 2025
Issued
December 10, 2025
Completed
May 29, 2026
Expires
June 10, 2027
7
Plan Review Days — Total
7
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$2,700,000
Type
Commercial Construction
Issued
December 10, 2025
Location
Downtown
Contractor Information
Location & Map
Project Description
4th Flr Market Ready Construct blanket permit tenant improvements to future tenant on the fourth floor of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Full C
Primary use
Commercial
Parcel
DV0084986
Review cycles
1
Plan review days
7
Days in corrections
0
Expires
June 10, 2027