PERMIT #7116839-CN
1959 NE PACIFIC ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 9, 2025
In Review
1 cycle
Reviews Done
January 26, 2026
Ready to Issue
February 6, 2026
Issued
February 6, 2026
Completed
—
Expires
August 6, 2027
48
Plan Review Days — Total
48
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1959 NE PACIFIC ST, SEATTLE, WA Property
Montlake Neighborhood
Project Overview
Project Details
Value
$900,000
Type
Commercial Construction
Issued
February 6, 2026
Location
Montlake
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
UW Medicine Ophthalmology - 3rd floor, NN300 Construct tenant improvements for medical clinic (UW Medicine Ophthalmology) east area on 3rd floor of existing institutional building, per plan. Mechanical included.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Institutional
Parcel
DV0010348
Review cycles
1
Plan review days
48
Days in corrections
0
Expires
August 6, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0