PERMIT #7117105-CN
9631 46TH AVE SW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
December 23, 2025
In Review
2 cycles
Reviews Done
February 11, 2026
Ready to Issue
February 12, 2026
Issued
February 12, 2026
Completed
March 30, 2026
Expires
August 12, 2027
50
Plan Review Days — Total
40
Plan Review Days — City Control
10
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
9631 46TH AVE SW, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$16,818
Type
Residential Construction
Issued
February 12, 2026
Location
Other Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
AADU, permit to establish Use Allow new attached accessory dwelling unit to existing single-family use, per land use code. Construct new one family dwelling, per plan. Construction alterations for two family dwelling, per plans.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0039050
Review cycles
2
Plan review days
50
Days in corrections
10
Expires
August 12, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0