PERMIT #7117116-CN

1505 Westlake AVE N, Seattle, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 17, 2025
In Review
0 cycles
Ready to Issue
November 18, 2025
Issued
November 19, 2025
Completed
March 11, 2026
Expires
May 19, 2027
0
Days in Applicant Control
0
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$200,000
Type
Commercial Construction
Issued
November 19, 2025
Location
South Lake Union

Contractor Information

Contractor
T C I INC
General Contractor
License TCIIN**077OO

Location & Map

Project Description
SRM 4th Floor STFI Tenant improvements to existing medical office (Pinnacle Fertility) on 4th floor of existing commercial building, subject to field inspection.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TCIIN**077OO
Housing category
Commercial Add/Alt
Review level
Field
Primary use
Commercial
Parcel
DV0037803
Review cycles
0
Days in corrections
0
Expires
May 19, 2027
Open official SDCI detail →