PERMIT #7117147-CN

1120 DENNY WAY, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 2, 2025
In Review
0 cycles
Reviews Done
January 15, 2026
Ready to Issue
January 17, 2026
Issued
January 17, 2026
Completed
Expires
July 17, 2027
44
Plan Review Days — Total
44
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$300,000
Type
Commercial Construction
Issued
January 17, 2026
Location
Downtown

Contractor Information

Contractor
ONNI BOREN AVE SEATTLE LLC
General Contractor
License ONNIBBA781MO

Location & Map

Project Description
Construction Permit Construct alterations to existing mixed-use building at P2 basement level for pedestrian tunnel connection, per plan. (Construction pedestrian tunnel in right of way to connect two mixed-use buildings, per plan. Review and process for 2 CN's under 7115874-CN.)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ONNIBBA781MO
Review level
Dependent Building
Primary use
Commercial
Parcel
DV0082667
Review cycles
0
Plan review days
44
Days in corrections
0
Expires
July 17, 2027
Open official SDCI detail →