PERMIT #7117236-CN

10252 41ST AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 8, 2026
In Review
2 cycles
Reviews Done
February 19, 2026
Ready to Issue
February 28, 2026
Issued
February 28, 2026
Completed
Expires
August 28, 2027
42
Plan Review Days — Total
22
Plan Review Days — City Control
20
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$4,700
Type
Residential Construction
Issued
February 28, 2026
Location
Other Seattle

Contractor Information

Contractor
GROUNDWORKS
General Contractor
License GROUN**763O5

Location & Map

Project Description
Hollien - Foundation Reair Construct foundation repair with helical piers to existing one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0045206
Review cycles
2
Plan review days
42
Days in corrections
20
Expires
August 28, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor