PERMIT #7117313-CN

2701 23RD AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 8, 2026
In Review
2 cycles
Reviews Done
July 7, 2026
Ready to Issue
July 7, 2026
Issued
July 7, 2026
Completed
Expires
90
Plan Review Days — Total
75
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Beacon Hill Neighborhood

Project Overview

Project Details
Value
$175,808
Type
Residential Construction
Issued
July 7, 2026
Location
Beacon Hill

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Allow housing for one new attached dwelling unit within existing structure per land use code. Construct alterations to convert one-family dwelling to two-family dwelling per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0086834
Review cycles
2
Plan review days
90
Days in corrections
15
Units added
1
Units removed
0
Open Map