PERMIT #7117553-CN

603 3RD AVE W, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
December 29, 2025
In Review
2 cycles
Reviews Done
January 22, 2026
Ready to Issue
January 26, 2026
Issued
January 27, 2026
Completed
April 9, 2026
Expires
July 27, 2027
24
Plan Review Days — Total
15
Plan Review Days — City Control
9
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood

Project Overview

Project Details
Value
$15,000
Type
Residential Construction
Issued
January 27, 2026
Location
Other Seattle

Contractor Information

Contractor
Not published by SDCI
License PACIFCC852N4

Location & Map

Project Description
Regan Lee Stairs Replace exterior stairs north of existing apartment building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PACIFCC852N4
Review level
Full +
Primary use
Multifamily
Parcel
DV0021703
Review cycles
2
Plan review days
24
Days in corrections
9
Expires
July 27, 2027
Existing units
24
Units added
0
Units removed
0
Sleeping rooms
0