PERMIT #7117566-CN

5900 4TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 12, 2025
In Review
2 cycles
Reviews Done
January 14, 2026
Ready to Issue
January 15, 2026
Issued
January 15, 2026
Completed
Expires
July 15, 2027
33
Plan Review Days — Total
23
Plan Review Days — City Control
10
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Georgetown Neighborhood

Project Overview

Project Details
Value
$50,000
Type
Commercial Construction
Issued
January 15, 2026
Location
Georgetown

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
5900 4th Ave S - Construction - R90 LIGHTING Construct interior alterations and expand ground level office areas within commercial warehouse [NORTHWEST CORPORATE PARK], per plan.

Additional Details

Permit Intelligence
Work performed by
Commercial Property Owner
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0027951
Review cycles
2
Plan review days
33
Days in corrections
10
Expires
July 15, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map