PERMIT #7117770-CN

1501 30TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 26, 2025
In Review
5 cycles
Reviews Done
March 20, 2026
Ready to Issue
March 20, 2026
Issued
March 21, 2026
Completed
Expires
September 21, 2027
84
Plan Review Days — Total
150
Days in Applicant Control
5
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Mt Baker Neighborhood

Project Overview

Project Details
Value
$15,000
Type
Residential Construction
Issued
March 21, 2026
Location
Mt Baker

Contractor Information

Contractor
PRIME BUILDERS W LLC
General Contractor
License PRIMEBW743BW

Location & Map

Project Description
1501 30th Ave S Construct tenant improvements to add unit to existing multifamily building, occupy per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PRIMEBW743BW
Review level
Full +
Primary use
Multifamily
Parcel
DV0034807
Review cycles
5
Plan review days
84
Days in corrections
150
Expires
September 21, 2027
Existing units
3
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor