PERMIT #7117803-CN
7611 45TH AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
January 8, 2026
In Review
2 cycles
Reviews Done
February 11, 2026
Ready to Issue
February 11, 2026
Issued
February 11, 2026
Completed
April 6, 2026
Expires
August 11, 2027
34
Plan Review Days — Total
28
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$27,000
Type
Residential Construction
Issued
February 11, 2026
Location
Rainier Valley
Contractor Information
Location & Map
Project Description
Gilbert - foundation repair Construct foundation repair with helical piers to existing one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1202505
Review cycles
2
Plan review days
34
Days in corrections
6
Expires
August 11, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0