PERMIT #7118458-CN
1016 E PIKE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 18, 2026
In Review
2 cycles
Reviews Done
April 14, 2026
Ready to Issue
April 14, 2026
Issued
May 11, 2026
Completed
—
Expires
November 11, 2027
55
Plan Review Days — Total
15
Plan Review Days — City Control
40
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1016 E Pike ST, Seattle, WA Property
WASHINGTON GNRL CNTRCTRS CORP Contractor
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$170,138
Type
Commercial Construction
Issued
May 11, 2026
Location
Capitol Hill
Contractor Information
Location & Map
Project Description
1016 E Pike 3rd Floor Spec TI Construct tenant improvements in commercial building on 3rd floor, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WASHIGC796KK
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0008983
Review cycles
2
Plan review days
55
Days in corrections
40
Expires
November 11, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0