PERMIT #7118553-CN

2620 37TH AVE W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 9, 2026
In Review
3 cycles
Reviews Done
May 4, 2026
Ready to Issue
May 5, 2026
Issued
May 5, 2026
Completed
Expires
November 5, 2027
115
Plan Review Days — Total
46
Plan Review Days — City Control
69
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$239,248
Type
Residential Construction
Issued
May 5, 2026
Location
Magnolia

Contractor Information

Contractor
CADRE GENERAL CONTRACTORS LLC
General Contractor
License CADREGC806MH

Location & Map

Project Description
Construction Permit Establish use as single-family dwelling unit, per land use code. Construct new one family dwelling, per plan. Existing dwelling units to remain.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CADREGC806MH
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0361243
Review cycles
3
Plan review days
115
Days in corrections
69
Expires
November 5, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor