PERMIT #7119247-CN

1 S NEVADA ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 5, 2026
In Review
2 cycles
Reviews Done
June 15, 2026
Ready to Issue
June 15, 2026
Issued
June 15, 2026
Completed
Expires
161
Plan Review Days — Total
39
Plan Review Days — City Control
122
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
SoDo Neighborhood

Project Overview

Project Details
Value
$170,000
Type
Industrial Construction
Issued
June 15, 2026
Location
SoDo

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Excavation and construction of stormwater infrastructure per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Industrial
Parcel
DV0357559
Review cycles
2
Plan review days
161
Days in corrections
122
Units added
0
Units removed
0
Open Map