PERMIT #7119302-CN
7215 B 12TH AVE SW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 2, 2025
In Review
0 cycles
Reviews Done
May 18, 2026
Ready to Issue
May 19, 2026
Issued
May 19, 2026
Completed
—
Expires
November 19, 2027
167
Plan Review Days — Total
167
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$278,317
Type
Residential Construction
Issued
May 19, 2026
Location
West Seattle
Contractor Information
Location & Map
Project Description
Construction Permit Construct new one-family dwelling (Unit2), per plan. (Allow three new single-family dwellings per Land Use Code. Construct alterations to existing one-family dwelling and three new one-family dwellings, per plan. Review and processing for four records under 7102630-CN.)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
DNHOMHC838QN
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0019754
Review cycles
0
Plan review days
167
Days in corrections
0
Expires
November 19, 2027