PERMIT #7120176-CN
10215 12TH AVE NE, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
March 5, 2026
In Review
2 cycles
Reviews Done
May 27, 2026
Ready to Issue
May 28, 2026
Issued
—
Completed
—
Expires
—
83
Plan Review Days — Total
80
Plan Review Days — City Control
3
Days in Applicant Control
2
Review Cycles
Plan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
10215 12TH AVE NE, SEATTLE, WA Property
Maple Leaf Neighborhood
Project Overview
Project Details
Value
$323,622
Type
Residential Construction
Issued
N/A
Location
Maple Leaf
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct new one-family dwelling (SFR1) per plan. (Establish use for 2 attached dwelling units and 2 one-family dwellings per land use code Construct (2) one-family and (1) two-family dwellings per plan. Review and processing for two records under 7120176-CN)
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1199570
Review cycles
2
Plan review days
83
Days in corrections
3
Units added
4
Units removed
1