PERMIT #7120268-CN
760 ALOHA ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
February 18, 2026
In Review
1 cycle
Reviews Done
March 31, 2026
Ready to Issue
April 1, 2026
Issued
April 7, 2026
Completed
—
Expires
October 7, 2027
41
Plan Review Days — Total
41
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
760 ALOHA ST, SEATTLE, WA Property
D P INC GENERAL CONTRACTORS Contractor
South Lake Union Neighborhood
Project Overview
Project Details
Value
$760,000
Type
Commercial Construction
Issued
April 7, 2026
Location
South Lake Union
Contractor Information
Location & Map
Project Description
MangoApps Tenant improvement for offices (MangoApps) on 5th floor of existing commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
DPINCGC066BU
Housing category
Commercial Add/Alt
Review level
Full C
Primary use
Commercial
Parcel
DV0031452
Review cycles
1
Plan review days
41
Days in corrections
0
Expires
October 7, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0