PERMIT #7120269-CN

2008 1ST AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 6, 2026
In Review
2 cycles
Reviews Done
February 19, 2026
Ready to Issue
February 26, 2026
Issued
February 26, 2026
Completed
Expires
August 26, 2027
44
Plan Review Days — Total
39
Plan Review Days — City Control
5
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Queen Anne Neighborhood

Project Overview

Project Details
Value
$100,000
Type
Residential Construction
Issued
February 26, 2026
Location
Queen Anne

Contractor Information

Contractor
VALENCIA CONSTRUCTION
General Contractor
License VALENC*820KM

Location & Map

Project Description
McFarland ADU Allow new attached accessory dwelling unit (AADU) to existing single family use, per land use code. Construct alterations for a two family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VALENC*820KM
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1124446
Review cycles
2
Plan review days
44
Days in corrections
5
Expires
August 26, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor