PERMIT #7120728-CN

102 1ST AVE S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
January 5, 2026
In Review
2 cycles
Reviews Done
March 16, 2026
Ready to Issue
March 20, 2026
Issued
March 20, 2026
Completed
June 3, 2026
Expires
September 20, 2027
70
Plan Review Days — Total
59
Plan Review Days — City Control
11
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Downtown Neighborhood

Project Overview

Project Details
Value
$25,000
Type
Commercial Construction
Issued
March 20, 2026
Location
Downtown

Contractor Information

Contractor
MORIS CONSTRUCTION LLC
General Contractor
License MORISCL792J1

Location & Map

Project Description
Le Macaron TI Construct interior, non-structural alterations to coffee shop for café / dessert shop (Le Macaron) with walk-in freezer, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MORISCL792J1
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0014942
Review cycles
2
Plan review days
70
Days in corrections
11
Expires
September 20, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor