PERMIT #7120923-CN

6218 VASSAR AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 13, 2026
In Review
3 cycles
Reviews Done
June 18, 2026
Ready to Issue
June 22, 2026
Issued
June 22, 2026
Completed
Expires
66
Plan Review Days — Total
60
Plan Review Days — City Control
6
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$410,005
Type
Residential Construction
Issued
June 22, 2026
Location
Laurelhurst

Contractor Information

Contractor
SHOWTIME HOME RENOVATION LLC
Single Family/Duplex
License SHOWTHR808DF

Location & Map

Project Description
Parker Project Construct additions and substantial alterations to one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SHOWTHR808DF
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1197001
Review cycles
3
Plan review days
66
Days in corrections
6
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor