PERMIT #7121082-CN
332 N 137TH ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 23, 2025
In Review
2 cycles
Reviews Done
February 5, 2026
Ready to Issue
February 6, 2026
Issued
February 6, 2026
Completed
—
Expires
August 6, 2027
44
Plan Review Days — Total
44
Plan Review Days — City Control
0
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
332 N 137TH ST, SEATTLE, WA Property
Addition at 332 N 137TH ST Project
ARMADA DESIGN & BUILD INC Contractor
Broadview Neighborhood
Project Overview
Project Details
Value
$53,689
Type
Residential Construction
Issued
February 6, 2026
Location
Broadview
Contractor Information
Location & Map
Project Description
Addition/Alteration SFR Construct additions and alterations for existing one family dwelling, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ARMADDB898R3
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1157843
Review cycles
2
Plan review days
44
Days in corrections
0
Expires
August 6, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0