PERMIT #7121178-CN
200 SUE BIRD CT N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
December 15, 2025
In Review
0 cycles
Ready to Issue
December 15, 2025
Issued
December 15, 2025
Completed
February 26, 2026
Expires
June 15, 2027
0
Days in Applicant Control
0
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$500,000
Type
Commercial Construction
Issued
December 15, 2025
Location
Belltown
Contractor Information
Location & Map
Project Description
Pacific Science Center Gates Demo Demolition of existing field canopy structurers, ticketing booths at north end of Pacific Science Center, per STFI
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SELLEC*372N0
Housing category
Commercial Add/Alt
Review level
Field
Primary use
Commercial
Parcel
DV0081053
Review cycles
0
Days in corrections
0
Expires
June 15, 2027