PERMIT #7121489-CN
6318 22ND AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 16, 2025
In Review
0 cycles
Reviews Done
April 7, 2026
Ready to Issue
April 8, 2026
Issued
April 9, 2026
Completed
—
Expires
October 9, 2027
112
Plan Review Days — Total
112
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$424,797
Type
Residential Construction
Issued
April 9, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Construction Permit Construct SOUTH one-family dwelling (SFR 3), per plan. (Establish use as single-family residence, per land use code. Construct (3) one-family dwellings, per plan. Review and processing for (3) records under 7093436-CN.).
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HERNABL805RC
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV0002025
Review cycles
0
Plan review days
112
Days in corrections
0
Expires
October 9, 2027
Units added
1
Units removed
0