PERMIT #7121533-CN

10350 EAST MARGINAL WAY S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
January 16, 2026
In Review
2 cycles
Reviews Done
April 1, 2026
Ready to Issue
April 2, 2026
Issued
April 3, 2026
Completed
Expires
October 3, 2027
75
Plan Review Days — Total
37
Plan Review Days — City Control
38
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$60,000
Type
Commercial Construction
Issued
April 3, 2026
Location
Other Seattle

Contractor Information

Contractor
RYAN COMPANIES US INC
General Contractor
License RYANCCU886BP

Location & Map

Project Description
Construction Permit Construct alterations to existing parking lot, per plan. Allow accessory cargo terminal to existing warehouse use, per land use code.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
RYANCCU886BP
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0362920
Review cycles
2
Plan review days
75
Days in corrections
38
Expires
October 3, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0