PERMIT #7121560-CN

4052 WILLIAMS AVE W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 16, 2025
In Review
0 cycles
Reviews Done
July 1, 2026
Ready to Issue
July 1, 2026
Issued
July 1, 2026
Completed
Expires
197
Plan Review Days — Total
197
Plan Review Days — City Control
0
Days in Applicant Control
0
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Magnolia Neighborhood

Project Overview

Project Details
Value
$219,389
Type
Residential Construction
Issued
July 1, 2026
Location
Magnolia

Contractor Information

Contractor
Alexander Hiebert
Single Family/Duplex

Location & Map

Project Description
Construct new one-family dwelling (South DADU) per plan. (Establish use as single-family residence with detached accessory dwelling unit per Land Use Code. Construct two new one-family dwellings per plan. Review and processing for two records under 7100718-CN.)

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Dependent Building
Primary use
Single Family/Duplex
Parcel
DV1133926
Review cycles
0
Plan review days
197
Days in corrections
0
Units added
1
Units removed
0
View Contractor