PERMIT #7121621-CN

3425 9TH AVE W, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
December 17, 2025
In Review
0 cycles
Ready to Issue
December 30, 2025
Issued
Completed
Expires
0
Days in Applicant Control
0
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Fremont Neighborhood

Project Overview

Project Details
Value
$10,000
Type
Residential Construction
Issued
N/A
Location
Fremont

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Complete and Final permit 6878374-DM.Demolish existing duplex and detached structure per STFI

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV1103766
Review cycles
0
Days in corrections
0
Open Map