PERMIT #7121670-CN

1519 12TH AVE, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
January 27, 2026
In Review
3 cycles
Reviews Done
July 8, 2026
Issued
Completed
Expires
162
Plan Review Days — Total
128
Plan Review Days — City Control
34
Days in Applicant Control
3
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Capitol Hill Neighborhood

Project Overview

Project Details
Value
$2,200,000
Type
Commercial Construction
Issued
N/A
Location
Capitol Hill

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to replace rooftop VAV air handling unit heat pump remove boiler and alterations to VAV boxes and addition of Energy Recovery Ventilators at existing municipal building (Seattle Police - East Precinct) per plan. Mechanical work included with this permit.

Additional Details

Permit Intelligence
Review level
Full C
Primary use
Institutional
Parcel
DV0019807
Review cycles
3
Plan review days
162
Days in corrections
34
Units added
0
Units removed
0
Open Map