PERMIT #7121969-CN

8015 21ST AVE NW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
February 13, 2026
In Review
2 cycles
Reviews Done
March 25, 2026
Ready to Issue
March 26, 2026
Issued
March 26, 2026
Completed
Expires
September 26, 2027
40
Plan Review Days — Total
34
Plan Review Days — City Control
6
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$140,884
Type
Residential Construction
Issued
March 26, 2026
Location
Ballard

Contractor Information

Contractor
ALAIR HOMES SEATTLE
General Contractor
License ALAIRHS753RE

Location & Map

Project Description
Piper's Palace Construct additions and alterations to existing single family residence, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ALAIRHS753RE
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1092042
Review cycles
2
Plan review days
40
Days in corrections
6
Expires
September 26, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
3
Open official SDCI detail →
View Contractor